Sprint Reviews — Project Pulse
The whole delivery arc at a glance. 12 cycles reviewed · 2026-02-23 → 05-31 · latest health 36 ▼ (down from 41). Each cycle drills down to its full review.
Health Trajectory
How the cycle health score moved across the quarter. The shaded bands mark the rating zones — green ≥ 75 (Good), gold 60–74 (Needs attention), red < 60 (Intervention).
The schedule story in one line
Healthy, small cycles in Feb–Mar (health 56–82) → the VNPAY onsite pivot (WK17–20) ballooned commitments to ~100/cycle while capacity held, crashing health to 22–28 and piling up 56–66 carry-overs each week → partial recovery in WK21–22 (41→36). The team ships a steady ~40–67 items/cycle — the collapse is a commitment-discipline problem, not a delivery one. WK16 & WK18 have no recorded review.
Throughput vs Commitment
Committed (track) vs completed (fill) per cycle. The widening gap from WK17 on is the over-commitment opening up.
All Cycles
Every reviewed cycle, color-coded. Click a cycle to open its full review.
| Cycle | Period | Health | Committed | Done | Completion | Carry-over | Cancelled |
|---|---|---|---|---|---|---|---|
| WK22 | From 2026-05-25 To 2026-05-31 | 36 | 100 | 50 | 50% | 48 | 2 |
| WK21 | From 2026-05-18 To 2026-05-24 | 41 | 122 | 67 | 55% | 44 | 11 |
| WK20 | From 2026-05-11 To 2026-05-17 | 28 | 97 | 40 | 41% | 56 | 1 |
| WK19 | From 2026-05-04 To 2026-05-10 | 23 | 100 | 34 | 34% | 66 | 0 |
| WK17 | From 2026-04-20 To 2026-04-26 | 22 | 98 | 34 | 34.7% | 62 | 2 |
| WK15 | From 2026-04-06 To 2026-04-12 | 75 | 63 | 61 | 96.8% | 0 | 2 |
| WK14 | From 2026-03-30 To 2026-04-05 | 67 | 67 | 51 | 76% | 14 | 2 |
| WK13 | From 2026-03-23 To 2026-03-29 | 48 | 73 | 44 | 60% | 27 | 2 |
| WK12 | From 2026-03-16 To 2026-03-22 | 76 | 32 | 30 | 94% | 0 | 2 |
| WK11 | From 2026-03-09 To 2026-03-15 | 82 | 26 | 23 | 88.5% | 0 | 3 |
| WK10 | From 2026-03-02 To 2026-03-08 | 56 | 36 | 24 | 67% | 12 | 0 |
| WK09 | From 2026-02-23 To 2026-03-01 | 79 | 16 | 15 | 93.8% | 0 | 1 |
Coverage & forward view
One row per cycle that has a recorded Plane sprint review. WK01–WK08, WK16 and WK18 have no review item. The current cycle WK23 (Jun 1–7) is in progress — see the Roadmap for the forward schedule.
The Four Phases of the Arc
1 · Foundation
WK09–12 · Feb–mid MarSmall, focused cycles (16–36 items, 67–94% done, health 56–82). Built Casbin RBAC, the Kafka/Debezium CDC pipeline, SMS/OTP, onboarding, and tax/ledger foundations.
2 · Scale-up
WK13–15 · late Mar–AprCycles doubled to 63–73 items. WK13 over-reached (60%, health 48), but WK14–15 stabilised — up to 96.8% completion and health back to 75.
3 · VNPAY pivot crash
WK17–20 · late Apr–mid MayThe team was pulled onto the VNPAY onsite engagement. Commitments ballooned to ~97–100/cycle while real capacity held; completion collapsed to 34–41%, health to 22–28, and carry-over debt exploded to 56–66 each week.
4 · Recovery
WK21–22 · late MayRecord throughput (67 then 50 done) but still over-committed (122/100); health recovered to 41 then slipped to 36. ~44–48 carry-overs persist. The fix is commitment discipline, not delivery speed.
How a review is produced
| Step | Action |
|---|---|
| 1. Reconcile | Read every incomplete item and verify against code; fix mislabeled (done-but-open) tickets first |
| 2. Collect | Pull cycle data + git evidence; note which comparison cycles have a trustworthy frozen snapshot |
| 3. Score | 5-dimension health score (completion · predictability · balance · flow · quality) on the corrected board |
| 4. Report | Executive summary, delivery, team breakdown, carry-over, trend, forecast, action triggers |
| 5. Record | Publish here + as a Plane Report item (linked from each page) |