Sprint Review — WK19

Cycle 2026-05-04 → 05-10 · Recorded in Plane as BANA-1049. The Executive Summary is sourced from git; the metrics below mirror the Plane review.

23/100 — Intervention required
34%Completion (34/100)
66Carry-over (66%)
0%Cancelled (0)
100Committed (~2× avg)

Executive Summary

~232commits
12contributors
~33commits/day

Leadership takeaway

This week (04/05 – 10/05) the team kept shipping despite a third consecutive VNPAY-onsite week: the two biggest themes were the new merchant onboarding & launchpad in the client app and a commerce / inventory backbone (merchant v2, multi-level categories, units of measure, vendors, inventory locations).

  • Merchant Onboarding & Launchpad — New onboarding flow with identity-verification step, auto sign-in after sign-up, organizer root and merchant launchpad, plus welcome and greeting screens.
  • Commerce & Inventory Backbone — Merchant v2 creation, merchant-scoped services, multi-level categories, units of measure, vendors and vendor payment terms, inventory locations, and material aggregate with stock handling.
  • Merchant Settings Suite — Merchant create/edit forms with tax-code check, city/wards, e-invoices, finance wallet, payment settings, and sale-channel sections.
  • Product Workspace — New product module, product list and basic-info forms, category select, draft status, and per-location stock options.
  • Search & CDC Reliability — Search-engine integration for the launchpad, plus a Kafka circuit breaker, transient-vs-permanent error classification, and backlog heartbeat logging.
  • Identity & Licensing — Phone-OTP template service, unlink phone/email, token returned on sign-up, and free-trial license issuance.
  • Helpdesk & Tax — SLA-policy management with receipt-template services, the initial helpdesk schema, and VN administrative-unit / tax-info CDC into invoicing.

Sprint context — continued VNPAY onsite pivot (3 weeks total)

WK17, WK18, and WK19 all ran with 5 VNPAY POs onsite at NEXPANDO. The team worked direct with them on the MVP delivery; planned tasks/bugs were put on hold to prioritize VNPAY requests for the full 3-week period.

  • WK19's 100-item plan was never realistic given continued VNPAY load. The plan-of-record decoupled from the work-of-record.
  • The 66 carry-over items are deferred-for-VNPAY, not delivery failure.
  • WK20 is the first restart cycle — VNPAY pivot ends, normal cadence resumes.

Read every "low completion" / "carry-over" number below against this pivot.

Health Score: 23/100 — by the numbers (not a process verdict)

DimensionScoreWeightContribution
Completion40.0/10030%12.0
Predictability0/10025%0.0
Workload Balance2.6/10020%0.5
Flow (no carry-over)0/10015%0.0
Quality (no cancel)100/10010%10.0

Mathematically correct against the WK19 plan but does not reflect actual outcome. Treat as: "the cycle's plan-of-record was overtaken by continued VNPAY engagement."

Delivery

MetricWK19WK184-cycle avgTargetNote
Committed1001353.5Plan set without acknowledging continued VNPAY load
Completed341235Team produced its usual output (~34/wk)
Completion %34.0%92.3%77.5%85%Pivot, not failure
Cancelled0 (0%)1 (7.7%)2.5<7%
Carried over66 (66%)016.5<10%Deferred for VNPAY
Throughput/member2.81.02.92.0✅ raw output OK

Verdict: team produced its usual output (~34 items). The plan never matched reality given VNPAY load. WK19 was a continued-pivot week, not a delivery collapse.

Team Breakdown

Sums >100 because items have multiple assignees. Read against the pivot.

MemberTotalDoneCarryDone %Load /5Flag
Hai383357.9%38/5🔴 OVERLOADED + LOW COMPLETION
Phat.N38122631.6%38/5🔴 OVERLOADED + LOW COMPLETION
Khoa2872125.0%28/5🔴 OVERLOADED + LOW COMPLETION
Bach124833.3%12/5🔴 OVERLOADED + LOW COMPLETION
Thuong75271.4%7/5🟡 OVERLOADED
Tai61516.7%6/5🟡 OVERLOADED + LOW COMPLETION
Phuc.D6060%6/5🔴 OVERLOADED + LOW COMPLETION
Huy43175.0%4/5
Viet4040%4/5🔴 LOW COMPLETION
Toan3030%3/5🔴 LOW COMPLETION
Kien330100%3/5
Phat.C1010%1/5🔴 LOW COMPLETION

Workload max/min ratio = 38× — far above the 3× threshold. Real problem regardless of pivot.

Carry-Over Age Analysis (66 items)

Of 66 not-done items, ~36 are ≥3 weeks old (template rule: MUST split or cancel):

AgeCountRuleItems
≥10 weeks (zombie cluster)5MUST cancelBANA-344, 509, 512, 516, 538
5-9 weeks16MUST split or cancelBANA-620, 621, 628, 677, 704, 705, 729, 730, 750, 756, 759, 760, 764, 770, 772, 781
3-4 weeks~15MUST split or cancelBANA-789, 792, 793, 801, 803, 810, 855, 872, 876, 890–894, 902–907, 926, 928, 930
2-3 weeks~17review with assigneeBANA-932–938, 944, 945, 964–975
<2 weeks~13safe to transferBANA-985–987, 1030, 1037

The WK17 review already flagged 9 zombies (BANA-216, 344, 509, 512, 516, 538, 620, 621, 628). 8 are still alive in WK19 — no decision was forced. These predate the VNPAY pivot — not excused.

4-Cycle Trend

MetricWK16WK17WK18WK19Direction
Committed653613100volatile
Completed58341234■ flat output
Completion %89.2%94.4%92.3%34.0%▼ pivot
Carry-over00066▲▲▲ pivot accumulation

Team's actual delivery rate is steady (~34 items/wk). Plan-of-record decoupled from reality during 3-week VNPAY pivot.

Recommendations for WK20 (the restart)

  1. WK20 = restart cycle. Set capacity to ~40 items. Don't run another oversized sprint just because VNPAY pivot ended.
  2. Force-cancel the 5 zombie items (BANA-344, 509, 512, 516, 538) — they've outlived their original context.
  3. Triage carry-over before WK20 commits — split, cancel, or commit. No more "transfer and hope."
  4. Rebalance Phat / Hai / Khoa — three people each carrying 28-38 items is structurally broken regardless of VNPAY.
  5. Pivot protocol for future onsite engagements — when an unplanned engagement consumes >2 days of team capacity, explicitly cut the sprint plan at the start. Don't run two plans in parallel.
  6. Skip "Intervention required" retrospective — Health Score is misleading here. Run a brief VNPAY post-mortem instead: what shipped, what feedback came back, what to fold into WK20-22.

Action Triggers — re-read against pivot

TriggerFiredVerdict
Completion <75% (1 cycle)🟡 Pivot context — watch WK20 to see if it persists
Completion <75% × 2 cyclesnot yetWK20 is the test
Member >5 items🔴 Real problem regardless of pivot — fix
Carry-over age >2 wk✅ (~36 items)🔴 Real problem — predate pivot — fix in WK20 triage
Cancellation >15%
Workload max/min >3×✅ (38×)🔴 Real problem regardless of pivot — fix
Health Score <60✅ (23)Misleading — see Context note